Short answer: renovate from the outside in and from the structure out. Start with surveys and approvals, then strip out, structural work, roof and windows. Next comes first fix plumbing and electrics, then insulation and plastering, then kitchens and bathrooms, second fix and finally decorating and flooring. The Federation of Master Builders puts it simply: structural repairs, roofing, services and insulation come before final finishes.

Getting the order wrong means paying twice, for example re-plastering a wall to fit a new cable, or replacing a new floor after a leak upstairs. Here is the sequence in detail.

Refurbished open-plan dining and living room with alcove units, marble fireplace and an oak dining table

The 12 stages of a house renovation

1. Survey the house

Find out what you are dealing with before you plan. A building survey picks up damp, roof problems, movement and timber decay. Older houses may also need an asbestos survey before any strip out. The Health and Safety Executive warns that buildings built or refurbished before 2000 can contain asbestos.

2. Design, budget and approvals

Fix the layout and specification, then get planning permission if you need it, building regulations approval and party wall agreements with your neighbours. Our guides to planning in Brent and Barnet explain the rules.

3. Strip out and demolition

Remove old kitchens, bathrooms, floor coverings, damaged plaster and any walls coming out. Book skips and licences in advance. See our guide to skip and scaffolding licences in Brent.

4. Structural work

Steel beams for knock-throughs, new foundations for an extension, underpinning, chimney breast removal and any repairs to joists. Building control inspects at key points.

5. Roof, external walls and drainage

Make the house watertight. Repair or replace the roof, fix gutters and downpipes, repoint brickwork and sort out drains. Nothing inside lasts if water is still getting in.

6. Windows and external doors

Fit them before plastering so the reveals can be finished neatly. In a conservation area, check what is allowed first.

7. First fix

Electricians, plumbers and heating engineers run cables, pipes, waste and ducting while walls and floors are open. Decide where every socket, light, radiator and tap goes before this stage.

8. Insulation and plastering

Insulate floors, walls and lofts, then board and plaster. Fresh plaster needs time to dry before it can be painted.

9. Floors, screed and carpentry

Lay screed or new subfloors, hang internal doors, fit skirting and architraves, and build any joinery.

10. Kitchen and bathrooms

Fit units, sanitaryware, tiling and worktops. Our kitchen timeline shows how long this part usually takes.

11. Second fix

Sockets, switches, light fittings, radiators, taps and the boiler are connected and tested. Electrical work gets its certificate and building control signs off.

12. Decorating, final flooring and snagging

Paint, then lay carpets and finished floors last so they are not damaged. Walk round with your builder and list any snags to fix before the final payment.

Working room by room

Common sequencing mistakes

Frequently asked questions

In what order do you renovate a house in the UK?

Survey, design and approvals first, then strip out, structural work, roof and windows. After that comes first fix, insulation and plastering, kitchens and bathrooms, second fix, and decorating and flooring last.

Should I do the kitchen or bathroom first?

On a full renovation, both are planned together because they share plumbing and first fix. If you are doing them one at a time, start with the bathroom upstairs so any leaks or dust do not damage a new kitchen below.

How long does it take to renovate a 3 bedroom house?

It depends on how much work is needed. A cosmetic refresh can take a few weeks, while a full renovation with rewiring, replumbing, a new kitchen and bathrooms often takes several months. Structural work or an extension adds more time.

Can I live in the house during a full renovation?

Sometimes, but it is hard when the kitchen, bathroom, heating or power are out. Many people move out for the heaviest stages, such as strip out, first fix and plastering.

Planning a full renovation?

Soot Builders manages home refurbishments from strip out to final decoration, coordinating every trade in the right order. We work across Willesden Green, Kilburn, Hendon, Wembley and North West London. Call 07714 062987 or tell us about your house.

Soot Builders Ltd, 189 Walm Lane, London NW2 3BU.

Leave a Reply

Your email address will not be published. Required fields are marked *