Short answer: renovate from the outside in and from the structure out. Start with surveys and approvals, then strip out, structural work, roof and windows. Next comes first fix plumbing and electrics, then insulation and plastering, then kitchens and bathrooms, second fix and finally decorating and flooring. The Federation of Master Builders puts it simply: structural repairs, roofing, services and insulation come before final finishes.
Getting the order wrong means paying twice, for example re-plastering a wall to fit a new cable, or replacing a new floor after a leak upstairs. Here is the sequence in detail.

The 12 stages of a house renovation
1. Survey the house
Find out what you are dealing with before you plan. A building survey picks up damp, roof problems, movement and timber decay. Older houses may also need an asbestos survey before any strip out. The Health and Safety Executive warns that buildings built or refurbished before 2000 can contain asbestos.
2. Design, budget and approvals
Fix the layout and specification, then get planning permission if you need it, building regulations approval and party wall agreements with your neighbours. Our guides to planning in Brent and Barnet explain the rules.
3. Strip out and demolition
Remove old kitchens, bathrooms, floor coverings, damaged plaster and any walls coming out. Book skips and licences in advance. See our guide to skip and scaffolding licences in Brent.
4. Structural work
Steel beams for knock-throughs, new foundations for an extension, underpinning, chimney breast removal and any repairs to joists. Building control inspects at key points.
5. Roof, external walls and drainage
Make the house watertight. Repair or replace the roof, fix gutters and downpipes, repoint brickwork and sort out drains. Nothing inside lasts if water is still getting in.
6. Windows and external doors
Fit them before plastering so the reveals can be finished neatly. In a conservation area, check what is allowed first.
7. First fix
Electricians, plumbers and heating engineers run cables, pipes, waste and ducting while walls and floors are open. Decide where every socket, light, radiator and tap goes before this stage.
8. Insulation and plastering
Insulate floors, walls and lofts, then board and plaster. Fresh plaster needs time to dry before it can be painted.
9. Floors, screed and carpentry
Lay screed or new subfloors, hang internal doors, fit skirting and architraves, and build any joinery.
10. Kitchen and bathrooms
Fit units, sanitaryware, tiling and worktops. Our kitchen timeline shows how long this part usually takes.
11. Second fix
Sockets, switches, light fittings, radiators, taps and the boiler are connected and tested. Electrical work gets its certificate and building control signs off.
12. Decorating, final flooring and snagging
Paint, then lay carpets and finished floors last so they are not damaged. Walk round with your builder and list any snags to fix before the final payment.
Working room by room
- Work from the top down. Finish the loft and top floor before the ground floor, so dust and debris do not land on finished rooms.
- Do wet rooms early. Bathrooms and the kitchen involve the most trades, so they set the pace.
- Keep one room as a clean base if you are living in the house during the work.
Common sequencing mistakes
- Decorating before the electrician has finished.
- Fitting a new kitchen before replacing a leaking roof or old pipework.
- Laying expensive flooring before the plaster has dried and the trades have left.
- Ordering windows late and holding up plastering.
- Starting work before the party wall notice period has ended.
Frequently asked questions
In what order do you renovate a house in the UK?
Survey, design and approvals first, then strip out, structural work, roof and windows. After that comes first fix, insulation and plastering, kitchens and bathrooms, second fix, and decorating and flooring last.
Should I do the kitchen or bathroom first?
On a full renovation, both are planned together because they share plumbing and first fix. If you are doing them one at a time, start with the bathroom upstairs so any leaks or dust do not damage a new kitchen below.
How long does it take to renovate a 3 bedroom house?
It depends on how much work is needed. A cosmetic refresh can take a few weeks, while a full renovation with rewiring, replumbing, a new kitchen and bathrooms often takes several months. Structural work or an extension adds more time.
Can I live in the house during a full renovation?
Sometimes, but it is hard when the kitchen, bathroom, heating or power are out. Many people move out for the heaviest stages, such as strip out, first fix and plastering.